We decided to build our own offices on some land we own as a cost saving exercise. I was sat in my office on the morning that the timber frame arrived and had a phone call to say that the timber frame erectors were off sick as the foreman had pulled a muscle in his back.It was 7:30 in the morning, i had 8 weeks to move out of our offices, a lorry load of wood turning up and no one to get the project started. I handed my workload to my right hand man Steve Hallam who is our contracts manager and headed home to do it myself. Eight weeks later, (and with a week to spare) we were moving in. I had a pulled on all my resources, colleagues and friends, basically anyone i had worked with and knew were good was involved.